Here is the space untouched... we will be leaving most of the ceiling exposed for an industrial look. We also plan on keeping the floors concrete, Obviously, we will be putting a ceiling and carpeting in the yoga room.

July 4, 2005

The concrete has been cut to rough in the plumbing. This is being done July 7th & 8th, and we should have inspections July 11. Then comes the concrete fill, framing and drywall construction.

width=32
width=32
July 15, 2005

With the plumbing trench filled and concrete poured lines can now be snapped and the walls framed. Here is the start of the yoga room walls being put up.

July 22, 2005

Most of the walls are framed out. You are looking down the hallway from the front dest area... the yoga room is on the left and the locker rooms on the right.

width=32
width=32
July, 22, 2005

This is another view of the walss framed out but from the inside of the yoga room. There are 11 windows along the top of the yoga room walls to allow for natural lighting. I am framing them out in wood and will be finished this weekend!

| about bikram | our school | schedule & rates | communication | FAQ's | home
For more information or to find a class while traveling, visit the Official Bikram Website here.
Developed and hosted by InterTotal.com
©2005